Home / Themed Playgrounds / Exhibit fabrication
Buyer guide · Museum exhibitions

Science Museum Exhibit Fabrication: How to Specify Hands-On Exhibits

Five stages from brief to opening, eleven RFP clauses you can copy into a tender, and why a prototype is not a luxury — written by the fabricator, for the person who has to write the specification.

By Great Adventurer Engineering Team ·Updated 9 November 2026 ·11 min read
The short answer. Exhibit fabrication is not a product order — it is a design-and-build contract with five distinct stages, and the specification you write at the start decides whether the gallery opens on time. This page is the checklist we work from as the fabricator:
  • Five stages — concept, prototype, detailed drawings, production, on-site commissioning
  • Eleven RFP items — wording you can paste straight into a tender document
  • One rule — never approve detailed drawings before a prototype has been in front of children

Museums and science centres buy differently from family entertainment centres. An FEC buys a proven product, installs it in a month and opens. A museum buys an exhibit: something that has to carry an educational intent, survive a decade of unsupervised use, fit a gallery whose walls are already built, and pass a fire and safety review that a shopping mall never asks for. The supplier, the contract and the questions are all different.

This guide is written for the person on the museum side who has to write the specification — often a curator or exhibitions manager, not a procurement specialist. It is deliberately specific, because vagueness at RFP stage is what produces change orders at installation stage.

A themed gallery in operation: sculpted structure, integrated lighting and hand-driven mechanisms in one build. Theme is cheap to vary at drawing stage and expensive to vary later.

Who this guide is written for — and who it is not

Museum / science centreFamily entertainment centre
What is being boughtAn exhibit with an interpretive intentAn attraction with a throughput target
Who signs offCurator, exhibitions manager, safety officer, sometimes a board or funderOwner or operations manager
Design controlClient holds design intent; fabricator executes itSupplier catalogue; client selects
DocumentationDrawings, material data sheets, O&M manuals, as-built setAssembly instructions
Opening constraintFixed public date, often tied to a funding milestoneCommercial target date
Cost of failureReputational and grant-related, not only revenueRevenue per closed day

If you are fitting out a commercial play centre, the water play cost guide and the ball wall guide are the closer match. What follows assumes an institution: a brief that has to be defended, an opening date that cannot move, and a building that will be occupied while you work in it.

The five stages, and what each one must produce

StageWhat it must produceSigned off byTypical duration
1. Interpretive briefLearning intent, station list, footprint, target age band, capacityCurator + exhibitions manager2–6 weeks
2. PrototypeFull-scale mock-up of the two or three highest-risk stations, tested with visitorsCurator + safety officer3–6 weeks
3. Detailed designFabrication drawings, structural calculations, electrical layout, material scheduleStructural engineer + client3–5 weeks
4. ProductionBuilt and factory-tested; mechanisms run before crating; video evidence recordedClient witness or QA inspection6–12 weeks
5. Installation and commissioningOn-site assembly, tuning, staff training, as-built set and spares handoverClient + safety officer1–3 weeks

Two things go wrong most often. Stage 2 is compressed to save calendar time, and stage 3 starts before the gallery's as-built drawings are confirmed. Both are decisions made by the client side, not the fabricator — which is why they belong in the RFP.

The eleven items your RFP must contain

These are the clauses that separate a tender that produces comparable bids from one that produces eleven incompatible documents. The wording in the right-hand column can be used as written.

#ItemWording to use
1Interpretive intent"Each station shall state the phenomenon it demonstrates and the intended visitor action. The exhibit as a whole shall support the following learning objectives: …"
2Station schedule"The fabricator shall provide a station schedule listing mechanism, intended age band, simultaneous users per station and target gallery throughput."
3Prototype requirement"A full-scale prototype of at least two stations shall be available for visitor testing for no fewer than ten operating days before detailed design approval."
4As-built fit"All exhibits shall be designed to the gallery as-built drawings dated … Any deviation requires written approval before fabrication."
5Structural information"The fabricator shall supply dead loads, dynamic loads, point loads and fixing details for review by the client's structural engineer."
6Materials and finishes"Wet or high-touch zones in 304 stainless steel or equivalent; material data sheets and a cleaning regime shall be supplied for every surface."
7Safety conformity"Exhibits shall comply with EN 1176 or ASTM F1487 as applicable. A conformity file including a per-station risk assessment shall be delivered."
8Fire and emissions"Combustible components shall meet the fire performance required by the authority having jurisdiction; VOC emissions of coatings and sealants shall be declared."
9Documentation set"As-built drawings, O&M manuals, a spare parts list with lead times, and a maintenance schedule in the client's working language."
10Working in an occupied building"Installation will take place while the museum is open. The fabricator shall provide hoarding, noise windows, dust extraction, daily clean-down and a named site supervisor."
11Acceptance and support"Per-station acceptance test, two days of staff training, a stated warranty period for mechanisms and electrical parts, and a remote support response time."
The clause that saves the most time later: item 4. A gallery that has been renovated twice rarely matches its original drawings, and every unverified dimension becomes a site modification at installation. Ask for a measured survey before detailed design, not after production.

Why the prototype cannot be skipped

A hands-on exhibit is judged in the first thirty seconds by people who cannot read the label and will not read the instructions. Almost every failure we see in prototype testing falls into six categories, and five of them are invisible on a drawing:

  • Force required. A crank that an adult turns easily can be impossible for a four-year-old. Torque has to be measured with a child, not estimated.
  • Reach and height. A mechanism placed at adult chest height excludes a third of the intended audience.
  • Splash and spill radius. Water travels further than the drawing suggests; the wet floor appears one metre outside the basin.
  • Climbability. Frames that were designed as structure become climbing frames the moment children arrive.
  • Pinch and trap points. Gaps of 8–25 mm are the classic hazard on hinged panels and sliding gates.
  • Jam behaviour. Balls, sand and water all find the one joint where the tolerance is wrong.

A prototype does not need to be a finished exhibit. It needs to be the actual mechanism, at full scale, with real children in front of it and someone recording what they do. Two stations are usually enough — the ones with the most moving parts, and the one the curator is least sure about.

Materials and standards, by market

MarketPlay equipment standardAdditional requirementsWhat we deliver
European UnionEN 1176 seriesCE marking, EN 71-3 migration where coatings are in contact with skin or mouthConformity file, per-station risk assessment, material data sheets
United KingdomEN 1176 as adopted in BS ENFire performance of textiles and foams to the venue's licence conditionsSame as EU, with test reports for upholstery and coatings
United StatesASTM F1487CPSIA where children's products are in scope; state fire codes for public assemblyCompliance statement, load calculations, installation drawings
ChinaGB 6675 seriesLocal fire code for public buildings; electrical inspection before energisingChinese-language manuals and acceptance documents
Gulf and Southeast AsiaUsually EN 1176 by referenceImport conformity and, in some markets, third-party inspection at originPre-shipment inspection support and a certification pack

Standards are a floor, not a design brief. Meeting EN 1176 says the exhibit will not injure a child in expected use; it says nothing about whether the mechanism teaches what the curator intended. Both questions belong in the contract, and they are answered by different documents.

Building inside a museum that stays open

This is the constraint that institutional buyers care about most and fabricators underestimate most. A gallery refit inside an operating museum is a logistics project with an exhibit attached:

  • Hoarding, not curtains. Full-height solid hoarding with a viewing window keeps dust in and lets visitors watch — the window is a public-relations asset, not a cost.
  • Noise windows. Core drilling, anchoring and steel cutting happen before opening or after closing. Written into the programme, not agreed day by day.
  • Delivery routes. A 4 m panel does not turn a 1.2 m corner. The route from loading bay to gallery is surveyed before production, not on delivery day.
  • Dust and fire watch. Extraction during cutting, and a hot-work permit procedure agreed with the venue's facilities team.
  • Isolation of services. Water and power connections are made during shutdown windows; temporary supply is planned for commissioning.

Our experience with themed builds — see themed playground equipment · ball science pavilion · scarf play equipment — is that a project which plans the occupied-building constraints at tender stage installs in a third less calendar time than one which negotiates them on site.

Support after opening

The exhibition opens, the fabricator leaves, and the exhibit becomes the facilities team's problem. What determines whether it still works in year three is decided before handover:

  • A spares list with lead times, not just part numbers. A seal that arrives in eight weeks is a closed station for eight weeks.
  • A wear-items schedule naming what will fail first — bearings, seals, cables, acrylic panels, tactile coatings — and when.
  • Remote troubleshooting. Photographs and a short video from staff resolve most mechanical faults without a site visit; agree the channel and the response time.
  • Training that is recorded. Staff turnover is the norm in museums; a fifteen-minute video of the maintenance routine outlives any handover session.

What to send us for a fabrication proposal

  • Gallery as-built drawings, or a measured survey with ceiling height and column positions
  • Interpretive brief: what the gallery is meant to teach, and to whom
  • Target age band and expected simultaneous capacity
  • Opening date, and whether the museum stays open during works
  • Standards and approvals the exhibit must satisfy, and who issues them
  • Any existing exhibit language — materials, colour, graphic style — the new work must match

With those six inputs we can return a stage-by-stage proposal with station list, materials, programme and responsibilities, rather than a single figure with a disclaimer attached. If you are earlier than that, the STEM gear wall range and unpowered water play equipment pages show the mechanism vocabulary we build from — most institutional briefs are assembled from those parts.

Need a number for your own space?

Send a floor plan or just the dimensions and ceiling height — we return an itemised quotation with station list, materials and freight assumptions. No obligation, typically within 48 hours.

Get an Itemised Quote on WhatsApp

Frequently asked questions

Do you work from our design, or produce your own?

Both. Most institutional projects arrive with a concept and an interpretive brief, and we develop it into fabrication drawings and a tested prototype. Where a museum has no design resource, we produce the concept stage as well — but the learning objectives and the interpretive voice stay with the curator, because that part cannot be outsourced.

What is the difference between exhibit fabrication and exhibit design?

Design decides what the visitor should understand and how the experience is sequenced. Fabrication decides how it is built so that it survives a decade of use, meets the applicable standards and can be maintained by the venue's own team. A single contract can cover both, but they are different skills, and a tender should say which one it is buying.

Can you match an existing gallery's visual language?

Yes — colour references, panel substrates, graphic style and lighting temperature are all matched from samples and photographs. What is harder to match is a mechanism built by a fabricator who no longer exists; in that case we reproduce the visitor-facing behaviour and document the internal differences, so maintenance staff are not working from two incompatible manuals.

How long does a gallery take from brief to opening?

For a single gallery of twelve to twenty stations, plan on four to seven months: two to six weeks of brief, three to six of prototype, three to five of detailed design, six to twelve of production, and one to three of installation and commissioning. The compressible stages are design and production overlap — not the prototype, and not the as-built survey.

Can exhibits be delivered to a fixed budget?

Usually yes, by fixing the station count early and treating the theming as the variable. Mechanism content is what costs money and what determines the educational value; finishes, graphic treatment and lighting can be phased or value-engineered without touching the mechanisms. Ask for the proposal to be priced in tiers against a fixed station schedule rather than as a single lump sum.